Duration

The duration of an activity is added by using numbers corresponding to days.

Duration can last from 0 to an infinite number of days.

A duration of 0 days, is called a milestone.

As seen below, a number corresponding to days is typed, and the right side of the gantt immediately shows the timeline being changed.

Dependencies

Besides giving activities a duration, it's important to make them dependent of each other.

This is used to showcase in which order the activities should be executed in.

As seen below the only action needed here is to tell each activity which other activity it is depended on.

The right side will show the changes made to the timeline.

Add dependency

Adding a dependency is done in two ways:

  • Opening the dependency menu with the mouse right click
  • Typing the row number of another activity

Dependency menu

When opening the menu the following options are available:

  • Activity: Which activities you want to depend on
  • Dependency: The type of dependency used (see below for details)
  • Delay: Add a delay corresponding to an amount of days
  • %: An alternative to the regular delay, stating that the activity can start/finish when a certain % of the dependent activity is passed  

Typing:

When typing the dependency, simply write the number of the row that you would like to make the activity dependent on.

Dependencies can be typed as:

  • Row number: The number of the row for the dependency
  • Type of dependency: Two letters representing the dependency type
  • Delay number: A number with the delay (a "-" symbol can be added to add a negative delay)
  • % symbol: Dictates if the delay number should be regarded as a percent

Below dependency examples.

Dependency types

There are 4 types of dependencies that can be used to create the timeline.

Finish to start

This is the default dependency type chosen by the system, as it's also the most commonly used.

This states that an activity can start when the dependent task is finished.

Start to start

This states that an activity can start when the dependent task is started.

Finish to finish

This states that an activity can finish when the dependent task is finished.

Start to finish

This states that an activity can finish when the dependent task is started.



Grouping exception

It's not possible to add dependencies to or from a group. Only dependencies between activities are valid. 