Before we introduce you to this part, we'll give you a learning of the basic elements.

The

...

essentials

Activities

When you are creating your gannt view it's build up by activities, which is a placeholder of the different types of objects which can be created or related to a project in Microbizz.

...

Duration, estimate, progress and dependencies

When you have created your activities and groups, you can now edit the duration, which is number of working days between the start- and end date.

Estimate is the estimated time for the activity which can be used when creating tasks afterwards.

Progress is a manual setting of the completion of the current activity or group. Group progress is automatically calculated with the sub activities.

Dependencies is used to set a relation between the start- and end dates of different activities.

See example of the use below.

Image Added

Types - Change activities to tasks, appointments or spacers

When the gannt view is created, you can now use type to change the activity to a task, appointment or spacer.

This is done by right-clicking on the type-icon and selecting the wanted object for the current activity.

Spacers are used to separate phases, to be able to make a better view of the current project if desired.

Tasks can be created as you click or it can be selected from a template, so next time you left-click it, it will go to the creation of the task with the selected template.

See example below.

Image Added


Existing tasks and appointments

It's possible to attach previously created tasks and appointments to new projects and it's shown below how to attach and select it in the project afterwards.

Image Added

Columns

Here you can set which columns from the objects that should be showed in the gannt-sheet below.

...