Here you can set up default styles, colors for the gannt view and work weeks for the project projects. These can be changed per project afterwards, but the default behavior is set up hereEach new project created, will use these settings. It's possible afterwards to change the settings per project.
The information is grouped into their type which is showed and explained below:
Tasks
...
This information is available in the gannt view and you can set up which information to be showed when viewing tasks in the gannt view.
It's possible to show information above, below, right and left each gannt element and depending on the gannt-type.
As seen in previous example above, we're showing task title, status, start- and end date in the gannt view.
Appointments
This information is available in the gannt view and you can set up which information to be showed when viewing appointments in the gannt view.
It's possible to show information above, below, right and left each gannt element and depending on the gannt-type.
As seen in previous example above, we're showing task title, status, start- and end date in the gannt view.
Group
...
, appointments, group, activity, project and placeholder
In these menu, you can customize the information show on the gantt acitivities for each type.
The customized information shown on the gantt.
Colors
In this menu you can change the default colors for new projects. This can be changes individually per project.
Work week
Choose a yearly calendar that the system should follow when planning gantt acitivities. For example holidays, special closed days and such.
It's possible to show information above, below, right and left each gannt element and depending on the gannt-type.
As seen in previous example above, we're showing task title, status, start- and end date in the gannt view.
Activity
This information is available in the gannt view and you can set up which information to be showed when viewing activity in the gannt view.
It's possible to show information above, below, right and left each gannt element and depending on the gannt-type.
As seen in previous example above, we're showing task title, status, start- and end date in the gannt view.
Colors
These colors are available in the gannt view and you can set up which colors to be showed when viewing the different elements in the gannt view.
As seen in previous example above, we're changing the displayed colors in the gannt view.
Work week
Doesn't work at the moment - to be continued.afterwards to choose another workweek each project should follow.
Gantt plans can be exported in PDF.
In this menu, you can decide which fields are included in the left side of the PDF where activities are shown in a list form.